Skip to main content

    Independent information and referral site. Not a utility, contractor or government agency. How we make money

    Commercial Solar Cost & Incentives

    Commercial Solar Installation Cost in California: What a Business Pays, 100 kW to 1 MW

    By Updated 16 min read

    MethodologyHow we make moneyEditorial policy

    For businesses, farms, schools and public agencies: installed cost by system size, the federal and state tax mechanics, what a commercial system saves on a business tariff, and what it does to a property's tax bill and value, worked through with sourced, dated figures rather than a sales estimate.

    A California business, farm or public agency installing a commercial system over 100 kW paid a median $2.0 to $4.1 per watt in 2023, depending on customer type, and commercial systems of 100 kW or less ran $2.5 to $4.3 per watt nationally (20th to 80th percentile), per Lawrence Berkeley National Laboratory's Tracking the Sun 2024 Edition (August 2024). Two dates now drive whether a commercial project captures the federal credit and the state property-tax break at all: a solar facility that began construction after July 4, 2026 must be placed in service by December 31, 2027 to get any federal Section 48E credit, and the California property-tax exclusion for solar goes inoperative on January 1, 2027. Verified September 23, 2026.

    This page covers commercial, agricultural and public-sector systems measured in kilowatts and megawatts. Pricing a system for a house? See what a home rooftop solar system costs in California instead; residential prices, tariffs and incentives work differently. The cost of a 10 kW home system is worked through on its own page, and the city guides cover home solar permit fees and utilities by California city, from Tracy to Arcata.

    Federal credit: December 31, 2027

    Section 48E does not apply to a wind or solar facility placed in service after December 31, 2027, unless construction began on or before July 4, 2026 . That date has already passed. Any California commercial solar project starting construction now needs a firm placed-in-service date no later than December 31, 2027, or the federal credit is zero .

    Property tax: inoperative January 1, 2027

    Revenue & Taxation Code §73 keeps a solar system's added value off your property's reassessed value. That exclusion goes inoperative January 1, 2027 . A system in process or completed before then keeps the exclusion permanently, until the property changes ownership; a system placed in service on or after January 1, 2027 currently gets none .

    See your own numbers

    Everything above is a published median or a statutory rule — not your building's numbers. The calculator below takes your system size, utility schedule and ownership structure and works through the same arithmetic this page walks through by hand: gross cost, the §48E credit, depreciation, an estimated bill offset, and a payback range. It is a planning tool, not a quote — a written proposal from a licensed contractor is the only number that actually binds anyone.

    Your building and bill

    1,622 kWh/kWdc-yr, PVWatts 100-kWdc fixed-tilt roof model.

    Blended rate: $0.20/kWh. For context only — PG&E B-10/B-19 source and SDG&E AL-TOU/TOU-M source summer on-peak energy rates run well above this blended figure, and demand charges are billed separately source; neither default is used in this calculator.

    Auto-sized to cover 80% of annual kWh at this location’s production factor. Override any time.

    California large non-residential (>100 kW), commercial customers, 2023 median. LBNL’s August 2026 update reports 2025 California medians of $3.2/W (100 kW or less) and $2.6/W (above 100 kW); enter either figure to use it (checked September 24, 2026) source.

    Tax position

    Construction starting after July 4, 2026 must be placed in service by December 31, 2027 to receive any §48E credit sourcesource.

    Federal 21% source · California 8.84% source.

    Export credit and escalation

    IOU NBT/Solar Billing Plan export values are hourly Avoided Cost Calculator prices, locked for 9 years — read yours from your utility’s NBT/SBP table. sourcesource

    Share of production used on site; the rest is exported.

    Default 3%/yr. The button fills the CAGR implied by CPUC Public Advocates Office 10-year residential rate data — residential, not commercial. sourcesourcesourcesource

    Estimated results

    Cost and tax benefits

    Gross installed cost (148 kWdc × $2.30/W)
    $340,400
    Federal ITC (§48E, 30.0%)
    $102,120
    Depreciable basis (gross − 50% of ITC)
    $289,340
    Federal year-1 depreciation tax value (100% bonus)
    $60,761
    California depreciation tax value (5-yr MACRS, no bonus)
    $25,578
    Net cost after tax benefits (undiscounted)
    Tax benefits arrive on tax returns, not at purchase. A business with no tax liability cannot use the credit without transferring it (§6418).
    $151,941

    Production and savings

    Year-1 production
    Self-consumed 168,039 kWh · Exported 72,017 kWh
    240,056 kWh
    Year-1 savings
    Exported energy valued at $0 — enter your export rate above. Demand-charge changes are not modeled; NBT export values vary hourly.
    $30,999
    Simple payback
    4.9 years
    25-year cumulative savings
    Includes rate escalation and production degradation.
    $1,032,098
    NPV at 8% discount rate
    $251,763
    IRR
    22.5%

    Property impact

    Property value indication (income approach)
    Year-1 NOI increase ÷ cap rate — an indication using the income-capitalization method appraisers use for income property sourcesourcesource. Not an appraisal; leased/PPA systems are treated differently sourcesource. Certification-based green-building premiums (LEED/Energy Star) are not solar-specific and are not included here source.
    $469,676
    Property tax
    Assessed value is not increased for this system under R&T §73 until a change of ownership (S catax-05/06/07). At the 1% base rate (Cal. Const. art. XIII A §1), that is the amount shown avoided per year — this treats the system’s installed cost as a stand-in for the assessed value the exclusion keeps off the roll. source
    $3,404/yr avoided

    What this leaves out

    • Demand charges. This model only values energy ($/kWh) savings; commercial rate schedules bill demand ($/kW) separately and solar typically reduces it only partially.sourcesourcesourcesourcesource
    • Batteries. SGIP’s general-market (non-equity) storage budget is currently shown closed to new commercial reservations.sourcesource
    • Prevailing wage on NEM/NBT systems over 15 kW. A separate compliance requirement (AB 2143) not reflected in the cost inputs above.source
    • Interconnection upgrades and Rule 21 fees. Application and, if required, supplemental/detailed-study fees and any distribution upgrade costs are not included in the installed cost above.sourcesourcesourcesource
    • Sales tax on fixtures. Most rack-mounted or ground-mounted commercial PV is taxed as a "fixture" on the contractor’s full selling price; this is not broken out separately above.sourcesource
    • REAP federal grants. Currently paused pending rulemaking; not assumed available.source

    This is an unofficial estimate built from public sources — not a quote, appraisal, or tax advice.

    Methodology and sources

    Installed cost by system size

    LBNL only publishes a state-level figure where at least 20 observations are available, and it splits non-residential systems into small (100 kW or less) and large (more than 100 kW) bands, so a single blended “commercial” average mixes two different markets and, in California, three different customer types. LBNL's newest update, published August 2026, reports non-residential installed prices as “essentially flat year-over-year” from 2024 to 2025 . Its medians for host-owned systems installed in 2025 are $3.2/W in California for 100 kW or less and $2.6/W above 100 kW ($3.1/W and $2.4/W nationally). The table below breaks the 2023 California figures down further, by customer type.

    Gross installed price, before incentives, by segment. California figures are 2023-installation medians; national figures are 2023 20th–80th percentile bands. Source: LBNL Tracking the Sun 2024 Edition. Verified September 23, 2026.
    SegmentSize bandPrice ($/W)Vintage
    California — commercial customers>100 kW$2.302023 installs
    California — agricultural customers>100 kW$2.002023 installs
    California — tax-exempt (nonprofit/gov't)>100 kW$4.102023 installs
    National — small non-residential≤100 kW$2.50–$4.302023 installs
    National — large non-residential>100 kW$1.70–$3.102023 installs
    National — commercial segment (industry)Any$1.71Q3 2025

    Industry pricing data corroborates the direction: SEIA and Wood Mackenzie's U.S. Solar Market Insight puts the national commercial segment at $1.71 per watt in Q3 2025, up 9% year-over-year from $1.57 in Q3 2024, driven mainly by a 50% year-over-year jump in racking and electrical balance-of-system costs offsetting cheaper modules — the first sustained increase in over a decade of declines.

    One caveat on NREL's figures, which show up often in solar pricing discussions: since 2023, NREL's annual “commercial” cost benchmark models a 3-MWdc ground-mount system, not a rooftop or carport project in the 25 kW–1 MW range most California businesses build . Its 2024 figure, $1.55 per watt (NREL/TP-7A40-92536), should not be read as a rooftop number. NREL's last rooftop-scale (200 kW) commercial benchmark, from Q1 2022, was $1.84 per watt modeled market price (NREL/TP-7A40-83586) — four years stale, but still the most recent size-appropriate NREL figure .

    For a manufacturing or warehouse site, an industrial system is reported in the same non-residential bands as any other commercial system of the same DC size; the operating profile (shift patterns, process heat, compressors, refrigeration) sets the demand curve, not a separate industrial price table. See warehouse solar and agricultural solar for the load-schedule questions those projects raise.

    Because a single average hides which side of the 100 kW split (and which customer type) a project sits on, work through the size-specific guides rather than a blended figure:

    For a line-by-line checklist rather than a benchmark, jump to what to ask every bidder to itemize before comparing price.

    What's in the price: cost breakdown

    NREL's 2024 component breakdown (on its 3-MW ground-mount model, so treat the total with the caveat above) splits as follows. Modules are priced per watt, so the panel count in a bid depends on what wattage commercial panels are.

    Component$/Wdc
    Module$0.35
    Inverter$0.06
    Balance of system (racking + electrical)$0.37
    Labor$0.36
    Soft costs (permitting, overhead, margin)$0.42
    Total (2024)$1.55

    For a rooftop-scale project, NREL's last granular breakdown (Q1 2022, 200 kW) itemized permitting, inspection and interconnection at $18,053 per project — about $0.09 per watt — including a $5,713 fixed permitting fee, a national average sales tax of 5.8% on hardware, EPC overhead of 13% on materials and 54% on labor, developer overhead of 30%, contingency of 4%, and profit margin of 7% . No NREL or LBNL source publishes a commercial carport-specific cost premium over rooftop; the only mounting-type coefficient either publishes ($0.40/W for ground-mounting) is explicitly scoped to residential systems, so ask a carport bidder to itemize the structural cost separately rather than assume a rule of thumb.

    Two buildings with the same annual kWh can still land on very different prices. Roof condition and remaining life, main switchgear and panel capacity, interconnection study results, whether the tariff's demand charges are modeled (not just annual kWh), mounting type, and ownership structure all move the number independently of system size. See PPA versus purchase and commercial financing options for how ownership changes both the price you sign and who keeps the tax benefit.

    What you actually pay: federal tax treatment

    A California business buying commercial solar in 2026 claims the credit under 26 U.S.C. §48E, the clean electricity investment credit. The statute sets a 6% base rate and a 30% rate for a facility with a maximum net output under 1 MW AC or one meeting the prevailing-wage and apprenticeship requirements. Bonus amounts exist for energy communities, domestic content and certain low-income sites, each with its own test; the domestic manufactured-products share the statute requires is 50% for projects beginning construction in 2026 and 55% after December 31, 2026. As the callouts above state, the credit does not apply to solar property placed in service after December 31, 2027 when the facility began construction after July 4, 2026. Confirm any rate or bonus with a tax professional before counting on it. The bonus tests, the foreign-entity rules, selling the credit and recapture are covered in what the §48E credit rules say in 2026.

    On depreciation, 26 U.S.C. §168(e)(3)(B)(viii) classifies §48E qualified property and energy storage technology as 5-year property, and §168(k)(1)(A) provides a 100% first-year allowance for qualified property, which applies to property acquired after January 19, 2025. Under §50(c)(3), the depreciable basis is reduced by 50% of the credit, not the full credit. Here is the federal arithmetic on a representative project:

    Illustrative arithmetic on statutory rules, not a published LBNL/IRS figure and not tax advice. Federal treatment only; see California non-conformity below.
    StepAmount
    System cost$500,000
    Credit at 30% (§48E(a)(2))$150,000
    Basis reduction, 50% of the credit (§50(c)(3))$75,000
    Depreciable basis$425,000
    Year-1 federal depreciation deduction if the 100% allowance applies (§168(k))$425,000

    The credit and the deduction are different mechanisms. The credit reduces tax owed dollar for dollar. The deduction reduces taxable income, so what it is worth depends on your entity's tax rate and whether it has enough income to use it. Ask your tax professional to run both on your own return.

    California does not conform to §168(k), and in general does not conform to the 2025 federal legislation that restored the 100% allowance, according to the FTB's 2025 Form 100 booklet, so the state deduction differs from the federal one. The same booklet lists an 8.84% tax rate for corporations other than banks and financial corporations and an $800 minimum franchise tax. Have a tax professional compute the California depreciation schedule and basis.

    The credit can be transferred to an unrelated taxpayer under §6418, though not to a specified foreign entity, and tax-exempt and governmental entities can elect to receive it as a payment under §6417. For construction beginning after December 31, 2025, §48E also denies the credit where a facility includes material assistance from a prohibited foreign entity, so panel, inverter and racking sourcing should be documented before relying on the full amount. Under §50(a), the credit is recaptured if the property is disposed of or stops qualifying within five years: 100% within the first full year after it is placed in service, then 80%, 60%, 40% and 20% in each following year.

    What commercial solar saves on the utility bill

    California's commercial tariffs price energy and demand separately, and demand charges — billed on the single highest metered kW in a period, not on total kWh — do not move nearly as much as a system's annual production does. A system that flattens most of a building's energy use can still leave the one interval that sets the demand charge largely untouched, which is why storage controls belong on the same proposal as the panels, not treated as a separate line item.

    Selected commercial TOU schedules, Secondary voltage. Figures are the bundled or total electric rate on a non-event day; each utility also charges separate non-bypassable and public-purpose components. Verified September 22, 2026.
    Utility / scheduleCustomer/basic chargeSummer on-peak demandSummer on-peak energyEffective
    PG&E B-10 (medium)$11.37/day$20.50/kW$0.339/kWhMar 1, 2026
    PG&E B-19 (large, mandatory)$58.63/day$46.16/kW$0.186/kWhMar 1, 2026
    SDG&E TOU-M (medium, ≤100kW)$209.77/mo$30.34/kW*$0.319/kWhJun 1, 2026
    SDG&E AL-TOU-L (large, ≤500kW)$234.63/mo$69.09/kW$0.283/kWhJun 1, 2026

    * TOU-M's demand charge is non-coincident, applied to the higher of monthly maximum demand or 50% of annual maximum demand . Both SDG&E schedules also carry a wildfire-fund plus DWR-bond non-bypassable charge of $0.00591/kWh, constant across every period and season .

    Export compensation for anyone interconnecting on or after April 15, 2023 runs through the CPUC's Net Billing Tariff (D.22-12-056, adopted December 15, 2022): hourly, Avoided Cost Calculator-based values, locked in as a “vintage” for nine years from interconnection . PG&E's own billing system did not start billing business customers under its Solar Billing Plan until March 2026, roughly three years after the policy's effective date . SMUD, outside CPUC jurisdiction, pays a flat 9.6 cents per kWh for exported commercial, industrial and agricultural solar, effective June 1, 2026, regardless of time of day or season. SCE's current, non-real-time-pricing commercial TOU-GS tariff sheets and LADWP's current commercial $/kWh rate levels could not be verified from a primary source at publication — rather than estimate, we are saying so plainly and pointing you to each utility's own current rate page before you model a bill offset on either one.

    Does commercial solar raise a property's value?

    Both the Appraisal Institute's Commercial Green and Energy Efficient Addendum (2015) and the Appraisal Foundation's Valuation Advisory #9 (2018) direct appraisers to the income approach as primary for solar on income-producing property, using the cost approach as a check. Where solar is leased or under a PPA, VA-9 instructs appraisers to examine the contract terms for how they affect “the amount and durability of net income”, and both bodies flag the sales-comparison approach as limited by thin transaction data for specialized systems like solar .

    Peer-reviewed evidence isolating a solar-specific value premium for California commercial property does not exist. The closest research measures whole-building LEED/Energy Star certification, not solar in isolation: Eichholtz, Kok & Quigley found a roughly 3% contract rent premium and a 16% sale-price premium for certified office buildings in 2010, and a roughly 3% contract rent premium with a 13%-plus sale-price premium in a larger 2013 follow-up — labeled certification-based, not solar-specific. The closest solar-only figures are industry, not academic, and not Californian: CBRE found a 4.2% value uplift on logistics property from on-site rooftop solar in Continental Europe , and JLL documented two U.S. industrial-property case examples, 4.4% (New Jersey) and 3.7% (Baltimore-D.C.), from third-party rooftop-solar leases valued by discounted cash flow of the lease income. The well-established residential literature — LBNL's “Selling Into the Sun” (about $4/W, or roughly $15,000, for an average home) and a California-specific NBER study of San Diego and Sacramento County home sales (3.5–3.6%) — is residential and should not be applied to commercial property. National commercial cap rates were “broadly stable” around 6.6% in CBRE's H1 2026 survey, with no California-specific table publicly available.

    Ready to compare your solar options?

    California Rate Relief is a private referral service. You can request a solar review; provider availability, design and price are determined after review.

    Request Commercial Review

    Property tax, sales tax, and permit fees

    Under R&T §73, the construction or addition of an active solar energy system is excluded from “newly constructed” for reassessment purposes; storage devices and power-conditioning equipment through the point of electricity conveyance are included as part of the excluded system.The exclusion applies to commercial and industrial property, including utility-scale solar — a 2012 Board of Equalization annotation found no language restricting it (Assessors' Handbook annotation 610.0089) . Per BOE Letter to Assessors 2026/034 (September 1, 2026, the most current guidance available), the exclusion goes inoperative January 1, 2027; a system in process or completed before then keeps the exclusion until a subsequent change of ownership , and there is currently no successor statute for a system placed in service on or after that date. A separate filing rule, effective the same date, gives an initial purchaser of a newly built structure with incorporated solar three years to file the exclusion claim .

    On sales and use tax, CDTFA Regulation 1521 covers construction contracts. It treats solar panels that are accessory to a building or structure, such as rack-mounted panels on a roof, as “fixtures,” and building-integrated PV that functions as roofing, windows or walls as “materials”, a distinction that changes how sales tax applies to the contract. It also says a charge for labor to affix solar panels purchased in a completed condition to a mounting system is not taxable. CDTFA also administers a partial exemption for certain manufacturing, research and electric-generation equipment under R&T §6377.1; whether it reaches your business is a question for a tax professional.

    Permit fees are capped statewide by Government Code §66015 at $1,000 for a commercial system up to 50 kW, plus $7 per kW for the 51–250 kW portion, plus $5 per kW above 250 kW (effective through January 1, 2034) . Actual city schedules are often lower: San Diego charges $758 plan-check plus $290 inspection for the first 100 kW, and $264 plan-check plus $145 inspection for each additional 100 kW, plus a separate electrical permit fee (Information Bulletin 301) . Confirm your own jurisdiction's current fee schedule directly.

    Incentives and mandates

    SGIP's general-market non-residential storage budget, Large-Scale Storage, is at Step 5 ($0.25/Wh) and shown Closed for PG&E, SCE, SoCalGas and the Center for Sustainable Energy as of September 23, 2026; the Non-Residential Storage Equity ($0.85/Wh) and Equity Resiliency ($1.00/Wh) budgets are also shown closed. See our SGIP battery storage page (which carries a published correction) before assuming a reservation is available. USDA REAP grants (up to 50% of eligible cost for IRA-funded categories) are currently paused while the agency rescinds its prior notice and rewrites the underlying rule under Executive Order 14315; guaranteed loans, up to 75% of eligible project cost, remain open.

    C-PACE assessments are collected on the county property tax bill under Streets & Highways Code §5898.10/.20. Four DFPI-licensed program administrators currently operate statewide (Renew Financial/CaliforniaFirst, PACE Funding Group, FortiFi, and Ygrene), and commercial-focused providers PACE Equity (up to 30-year term, up to 30% of property value, non-recourse, fixed rate) and CleanFund (up to 100% of project cost) also operate here via county and JPA program agreements. Full mechanics, eligible improvements, and how to apply are on our CPACE financing page.

    For new construction, California's 2025 Energy Code (Title 24 Part 6, in effect for permits filed on or after January 1, 2026) mandates solar PV, and in most cases battery storage, under §140.10 for a broad list of nonresidential building types, sized at Solar Access Roof Area times 18 W/ft² for steep-sloped roofs or 14 W/ft² for low-sloped roofs. See our Title 24 requirements page for the full building-type list, sizing equations, and battery exceptions .

    On utility rebates: SMUD explicitly states it does not offer solar installation rebates, and PG&E, SCE, SDG&E and LADWP's current business pages show no PV cash rebate either — each offers interconnection, net billing, or (for storage) SGIP instead. SGIP itself is a CPUC-authorized, ratepayer-funded program, not a utility's own discretionary rebate.

    Timeline and interconnection

    PG&E's and SCE's Rule 21 interconnection fees are flat regardless of system size: an $800 application fee and a $2,500 supplemental-review fee at both utilities (confirmed for SCE) . PG&E's own posted timeline runs application review 10–20 business days, engineering review 15–95 business days across up to three phases, and, if grid upgrades are needed, implementation adds 3–12 months on top; once no upgrades are required, final inspection is within 30 business days and interconnection approval follows about 3 business days later.PG&E's Distribution Interconnection Handbook gives an overall typical range of 3–6 months for Simplified/Fast Track review, 3–7 months for Supplemental Review, and 4–10 months for a full Detailed Interconnection Study, with a 15-business-day initial Fast Track review.

    Separately, Assembly Bill 2143 requires prevailing wage on renewable facilities over 15 kW enrolled in NEM or the Net Billing Tariff at PG&E, SCE, or SDG&E, with certified payroll filed with the CPUC twice yearly through the SURGE portal . Confirm whether your project's interconnection tariff triggers this before pricing labor.

    Quote checklist: what every bidder should itemize

    A benchmark only helps if the bids you hold against it describe the same project. Start from one written scope and ask every bidder to state the DC system size, equipment, roof, ground-mount or canopy scope, electrical upgrades, storage, interconnection work, permits, engineering and service responsibilities. If the scopes differ, the totals do not describe the same system: a lower number can leave out site work, roof work, storage or an obligation that arrives later in the contract.

    Line items to receive in writing from every commercial solar bidder.
    CategoryWhat to receive in writing
    System and siteDC size, equipment, layout, roof, canopy or ground scope, structural work, electrical upgrades and exclusions.
    Cash priceA line-item cash price, taxes, fees, allowances, change-order conditions and which costs sit outside the bid.
    Utility and productionProduction assumptions, tariff and load inputs, grid imports and exports, demand assumptions, interconnection responsibilities and the remaining-bill estimate.
    Ownership and serviceOwner, maintenance, monitoring, insurance, warranties, roof access, removal, transfer and end-of-term terms.
    Payment structureEvery payment, financing or PPA term, escalation, fee, security interest, default term and sale or refinancing condition.

    Compare the same cash price and physical scope first. Then put financing, lease, PPA, tax and incentive assumptions on separate rows: a payment illustration does not replace the cash price, and a claimed tax result is not a reduction that applies to every owner. The CPUC's California Solar Consumer Protection Guide is written for residential customers, but its core advice, to make sure everything you were promised is written in the contract, applies to a commercial bid too.

    1. Request full proposals and every contract exhibit before deciding.
    2. Match technical scope and cash price across bidders.
    3. List production, tariff, incentive and remaining-bill assumptions beside their sources and dates.
    4. Review ownership, service, finance and property-transfer terms separately.
    5. Keep the final contract, change orders and supporting projections together.

    Choosing a commercial solar installer

    CSLB's C-10 (Electrical) and C-46 (Solar) classifications both explicitly cover photovoltaic installation. Verify the exact contracting entity and its current license, bond, and disciplinary record at the CSLB lookup before signing anything. Ask each bidder to state the DC system size and cash price separately from any financing terms; itemize roof work, electrical upgrades, storage, and interconnection separately from the solar-only price; put expected production, remaining utility bill, and interconnection assumptions in writing; and get ownership, warranty, transfer, and service responsibilities spelled out as their own contract terms, not assumed. See what to compare across commercial solar companies for the full comparison guide.

    California Rate Relief is a referral service. We are not a licensed contractor. This page does not quote a system price, install equipment, or determine project eligibility; every figure above is a published third-party benchmark or a statutory rule, dated and cited, not a live bid.

    Frequently asked questions

    How much does commercial solar cost per watt in California?

    California's most current size- and customer-specific figures come from LBNL's Tracking the Sun 2024 Edition, covering 2023 installations (published August 2024): large non-residential systems, over 100 kW, ran a median $2.3 per watt for for-profit commercial customers, $2.0 per watt for agricultural customers, and $4.1 per watt for tax-exempt nonprofit and government customers. Small non-residential systems, 100 kW or less, ran $2.5 to $4.3 per watt nationally in the same year. All figures are gross installed prices before any incentive.

    How much does a 100 kW commercial solar system cost in California?

    A 100 kW system sits at the boundary LBNL uses to split small and large non-residential pricing, so a blended average is not useful at that exact size. See our dedicated 100 kW commercial solar cost guide for the size-specific figures and the scope questions to ask each bidder.

    How much does a 1 MW commercial solar system cost in California?

    A 1 MW system falls well inside the large non-residential band, where 2023 California medians ran $2.0 to $4.1 per watt depending on customer type. See our 1 MW commercial solar cost guide for the size-specific breakdown, including how a project at this scale differs from a rooftop-only build.

    Is the federal solar tax credit still available for commercial projects in 2026?

    Yes, under 26 U.S.C. §48E, at 6% base or 30% for a facility with a maximum net output under 1 MW AC or one meeting prevailing-wage and apprenticeship rules. But the credit does not apply to solar property placed in service after December 31, 2027 when the facility began construction after July 4, 2026. That date has passed, so a project starting construction now must be placed in service by December 31, 2027 to get any credit at all. Confirm your project's construction-start facts with a tax professional.

    What is MACRS bonus depreciation, and does California allow it?

    Under 26 U.S.C. §168(e)(3)(B)(viii), §48E qualified property and energy storage technology are 5-year property, and §168(k) allows a 100% first-year allowance for qualified property acquired after January 19, 2025. Under §50(c)(3), the depreciable basis is reduced by 50% of the credit. California does not conform to §168(k), according to the FTB's 2025 Form 100 booklet, so the state deduction differs; have a tax professional compute the California side.

    Does installing commercial solar affect my property's taxes?

    Under Revenue and Taxation Code Section 73, the added value of an active solar energy system, including paired battery storage, is excluded from your property's reassessed value. That exclusion goes inoperative January 1, 2027. A system in process or completed before that date keeps the exclusion permanently, until the property changes ownership. Under current law, a system placed in service on or after January 1, 2027 gets no new-construction exclusion.

    Does commercial solar increase a property's value?

    Appraisers primarily use an income approach for solar on income-producing property, capitalizing the added or avoided income through the property's net operating income. There is no peer-reviewed study isolating a solar-specific value premium for California commercial property. The closest evidence is whole-building green-certification research (not solar-specific, and not California) and a handful of non-California industrial case studies from CBRE and JLL. Treat any premium as a income-approach question for your own appraiser, not a fixed percentage.

    What is the payback period for commercial solar in California?

    Payback depends on your utility tariff's demand charges, your export value under the Net Billing Tariff, your ownership structure, and whether you can use the ITC and depreciation directly. There is no single statewide payback figure we can responsibly publish. Use the calculator above with your own system size and utility bill, and see PPA versus purchase for how ownership changes who captures the tax benefit.

    Is a PPA or a direct purchase better for a California business?

    It depends on whether you can use the §48E credit and depreciation. A direct purchase captures both but requires capital and taxable income; a PPA or lease shifts those tax benefits to a third-party owner in exchange for no upfront cost and a monthly or per-kWh payment. See our PPA versus purchase guide for California-specific terms on both.

    What permits does a commercial solar project need in California?

    A commercial contractor licensed for solar work (typically a C-46 or C-10 license) pulls building and electrical permits from the local jurisdiction. Government Code Section 66015 caps the fee statewide at $1,000 for systems up to 50 kW, plus $7 per kW for the 51-250 kW portion, plus $5 per kW above 250 kW. Actual city fees are often lower — San Diego, for example, charges $758 for plan check plus $290 for inspection on the first 100 kW. Confirm your city's current schedule directly.

    For the size-specific breakdowns and ownership comparison referenced above, see 100 kW, 500 kW, 1 MW, and PPA versus purchase.

    Sources

    Every figure above traces to one of the primary sources below, checked September 22, 2026; the cost figures, tax statements and SGIP status were re-checked September 23, 2026. Rates, incentive budgets, and program status change; confirm anything you intend to rely on directly with the source.

    Request a commercial solar review

    Send your property and billing details. California Rate Relief collects the information for a solar referral; the provider confirms availability, design and price.

    10-digit US number, area code first.

    Submitting does not create a quote, approval, or obligation.

    California Rate Relief is a referral service. We are not a licensed contractor. California Rate Relief is compensated by a solar provider when a homeowner we refer signs an agreement. How we make money

    What a per-watt figure leaves out

    Compare each proposal's written scope before using a per-watt figure.

    Compare California solar installers

    Our installer reviews rest on public records: complaint categories, court dockets, company filings and license checks.

    Company notes above, including any bankruptcy, license revocation or restructuring, carry their own source and date and were last checked on 24 September 2026. Each company's review page sets out the fuller case behind them. Status can change after that date; confirm anything you intend to rely on.