California solar decisions
Solar Companies in Modesto, CA: Installer Counts and License Checks
Modesto's main electric utility, the Modesto and Turlock irrigation districts, is not in the state's solar interconnection data, which covers PG&E, SCE and SDG&E customers only, and lists one system at Modesto addresses in 2025. The table below covers Stanislaus County instead: 519 systems in 2025, led by Sunrun (190), Sig Solar, S.i.g. (74) and Bright Ops (40). It is a count from public records, not a ranking or endorsement: check each license and get at least three quotes.
California Rate Relief is a private solar referral service.
Key facts
- Electric utility
- MID or TID
- CEC map: about 78% of city land MID, 22% TID
- California Energy Commissionchecked Sep 23, 2026
- MID size cap
- 115% of demonstrated load
- Anticipated load is not counted
- Modesto Irrigation Districtchecked Sep 23, 2026
- City expedited permit
- 10 kW AC, no battery
- Filed in eTRAKiT; batteries take the standard route
- City of Modestochecked Sep 23, 2026
Installers who connected the most home solar systems in Stanislaus County in 2025
| Installer (name as reported) | Systems in 2025 | Jan 2024 to May 2026 | CSLB license |
|---|---|---|---|
| Sunrun | 190 | 388 | 750184 check |
| Sig Solar, S.i.g. | 74 | 164 | 997639 check |
| Bright Ops | 40 | 65 | 1020761 check |
| Citadel Roofing and Solar | 37 | 82 | 647149 check |
| Power Up Solutions LLC | 18 | 24 | 1113778 check |
| Tesla Energy Operations Inc | 16 | 21 | 888104 check |
| Better Earth Electric Inc | 10 | 19 | 1024460 check |
| Allen Electric Inc | 9 | 45 | 917826 check |
Counts from utility records, not a ranking or endorsement. Check each license's status and complaint history on the CSLB's Check a License page (checked Sept. 24, 2026). The data set covers PG&E, SCE and SDG&E customers only, so in Stanislaus County it counts the areas PG&E serves.
Source: California Distributed Generation Statistics (CPUC), Interconnected Project Sites data set, data through May 31, 2026 (checked Sept. 24, 2026).
Home solar in Stanislaus County by the numbers
PG&E approved 519 home solar systems in Stanislaus County in 2025, from 61 installers; the top three were named on 59% of them. The busiest year since 2021 was 2023, with 697 (2025: -26%). Another 167 were approved from January through May 2026.
2025 mix: 48% leased or on a power purchase agreement, 52% owned by the household; 49% with a battery; median size 6.8 kW DC.
| Year | 2021 | 2022 | 2023 | 2024 | 2025 |
|---|---|---|---|---|---|
| Systems connected | 508 | 667 | 697 | 584 | 519 |
Hiring a solar company in Modesto
Solar companies in Modesto answer to the electric district that serves the meter, not to PG&E. Most of the city is Modesto Irrigation District territory, where MID must approve the design before installation and caps system size at 115% of your demonstrated load; part of the city is Turlock Irrigation District territory, with its own rules. Get three written bids that name your district, then compare them on the checks below.
MID's steps come before the panels go up
MID lays out the order itself. The contractor submits a completed interconnection package to MID, in hard copy, and MID approves it or asks for corrections. Only then does the contractor pull the city or county permit and install. The contractor sends MID the final permit, MID performs its own inspection, and if that is clear MID installs the solar meter; after that the contractor can switch the system on. MID says an interconnection not completed within a year of its acknowledgment is cancelled, with one six-month extension available on request.
MID offers NEM 2.0 today and does not offer solar rebates. Its sizing rule is the one most likely to separate two Modesto quotes: a system may not exceed 115% of the meter's annual demonstrated load, anticipated load is not considered, and oversized applications are mailed back to the contractor. MID's solar line is (209) 526-7582. A bidder that sized your system for an EV you have not bought yet should show you how the design fits that cap.
If your meter is on TID
The Energy Commission's map places roughly a fifth of Modesto's land area in Turlock Irrigation District territory. TID tells customers that installing solar moves them to a self-generation rate schedule, and that each of those schedules carries customer, demand and time-of-use energy charges, with a monthly TID bill continuing after the system is on. TID asks its customers to call (209) 883-8254 or email solar@tid.org to go over those charges before signing a contract.
A proposal written for an MID or PG&E account will not model a demand charge, so if your bill comes from TID, ask each bidder to rebuild its savings figure on TID's self-generation rate.
Modesto's expedited permit has limits
The City of Modesto's expedited solar checklist, filed through eTRAKiT, applies to roof-mounted systems of 10 kW AC or less on one- or two-family homes that are utility-interactive and have no battery storage. The roof needs a single covering with no reroof overlay, the array may cover no more than half of the total roof area, and the plans must show three-foot fire access pathways and panels at least 18 inches from any hip or valley. If a home has a pool or other large load and a main service under 200 amps, the City requires electrical load calculations, and smoke and carbon monoxide alarms must be verified during the job.
Any system with a battery, or any item on the checklist answered no, goes through the City's standard permit review instead. Ask each bidder which route its design uses; a battery quote that assumes expedited timing is assuming something the checklist rules out.
What a Modesto quote needs to explain
| Check | Ask each bidder |
|---|---|
| Correct electric district | Use the utility on the meter’s bill. Select Other / not sure in the inquiry if it is MID. |
| Demonstrated usage | Ask the bidder to show the load evidence used for MID sizing; separate any future-load assumption. |
| Installation and activation | Itemize city/county permits, MID application, metering and utility inspection in the scope. |
A comparison to ask for
A bidder may add panels for an electric vehicle you intend to buy. For an MID meter, ask whether that design meets MID’s demonstrated-load rule before comparing the larger system’s price. Have the quote identify metering equipment and utility inspection work. Approval comes before installation.
Verify the company behind the Modesto quote
Match the business name and license number on each Modesto proposal to the CSLB record, then use our contractor verification steps, the quote comparison guide and the PPA, loan, lease and cash comparison. What you pay the utility today is on the Modesto rates and bills page.
Permit fees and the filing route are on the Modesto solar cost and permit page.
Modesto solar quote questions
Does MID offer solar rebates?
No. MID's solar program page says it does not offer solar rebates. It currently offers only NEM 2.0 for new solar interconnections.
Can I get Modesto's expedited solar permit with a battery?
Not under the City's expedited checklist, which is limited to utility-interactive systems of 10 kW AC or less without battery storage. A solar-plus-battery project goes through the standard permit review.
Should an MID quote use statewide NEM assumptions?
No. MID publishes its own solar program, sizing rules and interconnection process. Have each bidder name the applicable MID schedule.
Can a larger MID system be justified by an electric vehicle I may buy?
MID’s current instructions say anticipated load is not considered. Ask MID and the bidder to confirm the allowed design from your demonstrated usage before committing.
Before you sign anything in Modesto
Two of the contract terms that most often change what a quote really costs.
Ask for a competing quote
Start with the utility on your bill and what you pay in a typical month. Contact details come after that. Submitting does not guarantee that a provider will quote your project.
California Rate Relief is a referral service. We are not a licensed contractor. California Rate Relief is compensated by a solar provider when a homeowner we refer signs an agreement. How we make money
Before you send anything
- What this is
- California Rate Relief is a private referral service. It is not a contractor, does not install or finance anything, and is not a utility, a government agency or an assistance program.
- What happens after the form
- Your project details are recorded for referral to a solar provider. The provider decides whether it can help and what it can offer; availability, design and price are determined after its own review.
- How you are contacted
- Read the consent wording before submitting. Your inquiry includes contact details for follow-up about the project; a provider decides whether it can serve it.
- Using the site without submitting
- The calculators, bill comparisons and checklists on this site work without contact details, and nothing on this page requires a submission.